Carreteras y tráfico · Tenerife · 13.11, 06:02
Road safety works to begin at school in Tías
The Ayuntamiento in Tías has allocated 695 000 euro to improve safety on Calle Igualdad. Works will start within a few weeks.
Preparado por IA a partir de las fuentes siguientes. Nos aseguramos de que se ajuste a los hechos de las fuentes, pero la IA puede cometer errores - en caso de duda, prevalece la fuente. Traducido automáticamente del polaco. Cómo hacemos estos textos →

The company Transporte y Excavaciones Tiagua received the contract for the project. The project will last approximately 6 months. The plan includes new vertical and horizontal signage. It also includes improved lighting, the installation of shading elements, and earthworks and installation works. The goal is to protect students of the Alcalde Rafael Cedrés school from accidents.
Traffic disruptions may occur on Calle Igualdad in Tías during the coming months due to construction work.